10:26AM January 08, 2023

Ken Sharpe

Reconnect 2 has been awarded a grant. Any idea when we can connect in our home?

User Avatar

3:21PM January 12, 2023

Becky Mashburn
Hi, Ken. Good timing! We expect initial field work to begin on January 24. This work will focus mostly on prepping our system for the fiber construction – think tree trimming and pole replacements. After that is complete, we’ll begin constructing the Elevate network. Our best guess for bringing service into homes within the Reconnect 2 area is mid-summer 2023.